Complete list of current Q & A>> Download PMI Project Management Professional (PMI-PMP) – Quiz 1 / 15 Category: PMI Project Management Professional (PMI-PMP) 1. Changes in the report formats and lessons learned documents process should trigger changes to the A. Project management plan and performance reporting system B. Integrated change control system and the communications management plan C. Monitor and control project process and the project management plan D. Organizational process assets updates 2 / 15 Category: PMI Project Management Professional (PMI-PMP) 2. The purpose of work performance data in control communications is to present results of comparative analysis to the A. Performance measurement baseline B. Communications management plan C. Stakeholder management plan D. Deliverable status 3 / 15 Category: PMI Project Management Professional (PMI-PMP) 3. You are working on a project with 15 stakeholders. The number of communication channels on this project is A. 15 B. 105 C. 210 D. 225 4 / 15 Category: PMI Project Management Professional (PMI-PMP) 4. The risk urgency assessment is a tool and technique used for A. Plan risk responses B. Identify risks C. Perform qualitative risk analysis D. Perform quantitative risk analysis 5 / 15 Category: PMI Project Management Professional (PMI-PMP) 5. As project manager, you have assembled the team to prepare a comprehensive list of project risks. Which one of the following documents would be the most helpful in this process? A. OBS B. WBS C. RBS D. CBS 6 / 15 Category: PMI Project Management Professional (PMI-PMP) 6. The Delphi technique is a particularly useful method for identifying risks to A. Present a sequence of decision choices graphically to decision makers B. Define the probability of occurrence of specific variables C. Reduce bias in the analysis and keep any one person from having undue influence on the outcome D. Help take into account the attitude of the decision maker toward risk 7 / 15 Category: PMI Project Management Professional (PMI-PMP) 7. Most statistical simulations of budgets, schedules, and resource allocations use which one of the following approaches? A. PERT B. Decision-tree analysis C. Present value analysis D. Monte Carlo analysis 8 / 15 Category: PMI Project Management Professional (PMI-PMP) 8. Which term is NOT a common name for a procurement document that solicits an offer from prospective sellers? A. Contractor initial response B. Request for information C. Request for quotation D. Invitation for negotiation 9 / 15 Category: PMI Project Management Professional (PMI-PMP) 9. Which term describes the failure by either the buyer or the seller to perform part or all of the duties of a contract? A. Termination of contract B. Partial performance C. Breach of contract D. Contract waiver 10 / 15 Category: PMI Project Management Professional (PMI-PMP) 10. Contract type selection is dependent on the degree of risk or uncertainty facing the project manager. From the perspective of the buyer, the preferred contract type in a low-risk situation is A. Firm-fixed-price B. Fixed-price-incentive C. Cost-plus-fixed fee D. Cost-plus-a-percentage-of-cost 11 / 15 Category: PMI Project Management Professional (PMI-PMP) 11. Working to foster stakeholder engagement, as the project manager, you know a combination of interpersonal skills and general management skills is needed. An example of a key interpersonal skill in stakeholder engagement is A. Facilitating consensus B. Influencing people C. Resolving conflicts D. Negotiating agreements 12 / 15 Category: PMI Project Management Professional (PMI-PMP) 12. As you prepare to close out contracts on your project, you should review all the following types of documentation EXCEPT the A. Contract document for the contract being closed B. Procurement audit report C. Invoice and payment records D. Seller performance reports 13 / 15 Category: PMI Project Management Professional (PMI-PMP) 13. A communications management plan includes which one of the following sample contents? A. Issues B. Escalation processes, including time frames and the management chains C. Dimensions D. Project assumptions and constraints 14 / 15 Category: PMI Project Management Professional (PMI-PMP) 14. Work performance information is an output of which process? A. Manage risks B. Manage communications C. Control communications D. Report performance 15 / 15 Category: PMI Project Management Professional (PMI-PMP) 15. Information received from stakeholders concerning project operations can be distributed and used to modify or improve future performance of the project. This modification or improvement is done as an update to organizational process assets during which following process? A. Plan communications management B. Distribute information C. Manage communications D. Report performance Your score is 0% Restart quiz Send feedback