Complete list of current Q & A>> Download CompTIA Project+ (PK0-005) – Quiz 1 / 15 Category: CompTIA Project+ (PK0-005) A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation? A. ESG B. PHI C. PII D. ROIL 2 / 15 Category: CompTIA Project+ (PK0-005) During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use? A. Issue log B. Defect log C. Change log D. Task board 3 / 15 Category: CompTIA Project+ (PK0-005) Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration? A. Approving the change request B. Developing a rollback plan C. Gathering necessary resources D. Defining requirements 4 / 15 Category: CompTIA Project+ (PK0-005) During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer. Which of the following documents would the project manager need in order to find this information? A. SLA B. TOR C. SOW D. NDA 5 / 15 Category: CompTIA Project+ (PK0-005) A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information? A. RFI B. RACI C. WBS D. SOW 6 / 15 Category: CompTIA Project+ (PK0-005) By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule? A. Allocate resources. B. Determine the project budget. C. Develop a communication plan. D. Establish baselines. 7 / 15 Category: CompTIA Project+ (PK0-005) A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization’s reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Choose two.) A. Train users on the proper use of the system. B. Escalate the issue to the CCB. C. Hold sessions to understand user challenges. D. Track system usage and report user activity. E. Log the issue in the project risk register. F. Create a memorandum of acceptable use 8 / 15 Category: CompTIA Project+ (PK0-005) Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input? A. Daily stand-up B. Project momentum C. Performance feedback D. Meeting minutes 9 / 15 Category: CompTIA Project+ (PK0-005) Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint? A. Evaluating the project B. Releasing the resources C. Closing the contracts D. Reconciling the budget 10 / 15 Category: CompTIA Project+ (PK0-005) During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes? A. Ishikawa diagram B. Scatter diagram C. Pareto chart D. Decision tree 11 / 15 Category: CompTIA Project+ (PK0-005) Which of the following BEST describes how an organization should coordinate management of multiple related projects? A. Apply the SDLC process. B. Establish a program. C. Consult the CCB. D. Use different frameworks. 12 / 15 Category: CompTIA Project+ (PK0-005) A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments? A. Status report B. Project plan C. Change log D. Meeting minutes 13 / 15 Category: CompTIA Project+ (PK0-005) A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use? A. Synchronous B. Informal C. Asynchronous D. Formal 14 / 15 Category: CompTIA Project+ (PK0-005) As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process? A. Update the work breakdown structure. B. Review the backlog. C. Seek baseline approval. D. Establish the resource pool. 15 / 15 Category: CompTIA Project+ (PK0-005) A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT? A. Trigger the contingency plan and communicate with the stakeholders. B. Work with the functional managers to create a work-around. C. Submit a change request to the change control board. D. Transfer the risk by hiring a new vendor who was successful on a previous project. E. Set up an escalation meeting with the sponsor. Your score is 0% Restart quiz Send feedback